It is an industrial-type facility consisting mainly of mechanical and electrical data storage and processing equipment in the cloud and is structured as a main Equipment Building (ATH04 Building) and an Administration Building (Admin Block) accompanied by a number of supporting facilities and infrastructuresin the surrounding area, while the design follows LEED certification requirements(Gold Grade).
The construction contract amounting to 100 million euros (including VAT) covers the completion of
studies, construction, and commissioning of the first Microsoft Data Center with a total installed
capacity of 19.2MW in Spata. Construction works are expected to commence during the next period.